Garage Conversion ADU in Lomita, CA: What It Costs and How Long It Takes
A garage conversion ADU in Lomita typically runs $45,000 – $130,000 and takes 4 – 7 months from first demolition to final inspection. You’re turning an existing garage into a legal, rentable second dwelling: new foundation and slab work where needed, insulated walls and ceiling, a full bathroom and kitchenette, dedicated electrical and often a gas line, and a separate utility meter if you want the unit to stand on its own. Call (888) 345-8164 to schedule a free on-site estimate and written line-item quote.
How We Turn a Lomita Garage Into a Livable ADU

Every conversion follows the same backbone, but the duration at each stage depends on what’s under your slab and inside your walls. Here’s the real sequence on a Lomita garage conversion ADU.
Stage 1: Site walk and feasibility (week 1)
We measure the garage, check ceiling height and door opening, and look at where the main panel sits relative to the unit. You decide at this stage whether the kitchenette will be gas or all-electric, and whether you want a separate meter. On a small Lomita lot, the back-of-garage wall is often the shared property line, so this is also when we flag any setback or sight-line issue before drawings go anywhere.
Stage 2: Design, permits and plan check (weeks 2 – 10)
Full architectural drawings, then submittal to the City of Lomita’s building department. A small-city plan-check counter moves on its own schedule, and because Lomita reviews lot-by-lot rather than under a broad county template, plan check is where timelines stretch. We handle the submittal, respond to comments, and pull the permits. You confirm finishes while this is happening, so nothing stalls when the permit lands.
Stage 3: Demolition and shell prep (weeks 1 – 2 of construction)
The garage door comes off and gets framed in with a window and a standard entry door. Floors get addressed first: existing garage slabs were never poured to interior tolerances, so we level, insulate, and where the slab is badly cracked or below grade, pour new. This is the stage that decides your final number more than any other, because it’s where unexpected rot or a shallow footing shows up.
Stage 4: Rough-in and inspection (weeks 3 – 6)
Framing for the bathroom walls, plumbing runs (we try to keep the wet wall close to the existing drain line to limit trenching), electrical circuits, and HVAC or a ductless mini-split. Rough framing, plumbing, mechanical and electrical inspections happen back to back. You’ll be asked to lock in fixture and appliance choices before we close the walls.
Stage 5: Insulation, finishes and final (weeks 7 – 14)
Insulation, drywall, paint, tile, flooring, cabinets, fixture trim-out, and the final inspection. Then we walk the unit with you and hand over documentation. The whole thing is covered by our 730-Day Done Right Promise once we close out.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between for Your Garage Conversion ADU
Most of the cost swing on a garage conversion ADU comes from a handful of choices. Here’s what’s actually on the table and how each holds up.
- Kitchenette scope: A counter-and-sink nook with a cooktop runs at the low end. A full L-shaped kitchen with a range, hood, and full-size refrigerator adds real money but makes the unit rent more easily.
- Bathroom layout: A compact three-quarter bath (shower, toilet, vanity) is the standard, most cost-efficient choice. A full tub limits renters in a small footprint and adds floor space you may not have.
- Flooring: Luxury vinyl plank handles moisture and wears hard in a unit with its own entry door. Porcelain tile costs more to install but is the most durable in a wet-room zone. Carpet in an ADU is the wrong call.
- HVAC: A ductless mini-split is the usual pick because it avoids running ductwork through a low garage ceiling. You can also tie into the main house system, but that runs into capacity questions on older equipment.
- Metering: A separate electrical meter costs more upfront and speeds up rental arrangements. Shared metering is cheaper but complicates the lease.
- Roof and envelope: Many Lomita garages sit under aging composition shingles. If the roof is at end of life, replacing it during conversion is far cheaper than doing it later – Atlas and Tamko shingle lines are both solid mid-grade options here.
- Windows: Salt air and marine fog eat at cheaper hardware. PGT impact-rated units make sense on the PCH-facing side, though standard dual-pane with good flashing detail works on interior-facing walls.
Garage Conversion ADU Cost in Lomita, CA

Expect $45,000 – $130,000 for a garage conversion ADU in Lomita. The large majority of units land between $50,000 and $85,000; the high end is for larger garages with a full kitchen, new slab, and a separate meter.
What moves the number:
- Garage size and layout: A 400 sq ft single-car is simpler and cheaper than a 600 sq ft double. Every added square foot means more framing, insulation, and finish.
- Condition of the existing structure: Rotted framing, a cracked slab, or an undersized footing can add $8,000 – $20,000 depending on how much needs rebuilding.
- Relocating plumbing and electrical: Keeping the wet wall and panel close to existing runs saves several thousand dollars. Long trenching or a panel upgrade pushes toward the high end.
- Finishes: A contractor-grade kitchenette and LVP flooring versus a fully customized kitchen with tile and stone can easily be a $20,000 – $30,000 spread.
- Permit and plan-check scope: A full legal ADU with a separate meter, a full fire-separation review against the main house, and structural upgrades means more review time and higher permit fees than a simpler accessory structure.
Your written estimate will list framing, rough and finish plumbing and electrical, insulation, drywall, flooring, kitchenette, bathroom, HVAC, and permits – line by line. It typically won’t include landscaping, driveway restoration, or utility connection fees charged directly by the utility. Call (888) 345-8164 for an exact quote – estimates are free, and the number you see on the estimate is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhat Lomita Homes Specifically Do to This Job
Lomita is roughly one square mile, incorporated in 1964 and fully surrounded by Torrance, with essentially no undeveloped land left. Almost everything built here now is remodel, addition, ADU, or tear-down-rebuild work on tight infill lots, not new subdivisions. Most of the housing stock we work on in Lomita is 1920s – 1950s bungalows and early tract homes on 5,000 – 6,000 sq ft lots, with 1960s – 70s stucco apartments along the corridors near Pacific Coast Highway and Lomita Boulevard. That build era matters: garages from that period often have shallow footings, thin slabs, and framing that’s been quietly rotting behind old stucco for decades. We routinely find corroded fasteners and flashing from the salt air and marine fog, and it’s one reason we spec coated or galvanized hardware, not bare steel. Because Lomita runs its own building department, plan check is a lot-by-lot negotiation rather than a template, especially on small lots where a rear setback or second-story height limit gets reviewed against the neighbor’s roofline. That’s real work, and it’s why we start feasibility before drawings. If your conversion is part of a full Home Additions & ADU in Lomita plan, we scope the whole thing together. Covering Lomita and the surrounding South Bay is what we do, and this is a clear look at our Home Additions & ADU service.
Homeowners often pair a garage conversion with refreshed finishes in the main house as rental prep – our Cabinets & Countertops in Lomita work and Backsplash, Tile & Flooring in Lomita crew can run alongside the conversion for a coordinated finish.
Serving Lomita, CA – Our Local Coverage Area
We serve Lomita and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked Questions – Garage Conversion ADU in Lomita

Most Lomita garage conversion ADU projects take 4 – 7 months, with 4 – 10 weeks of that in design and plan check before construction starts. Construction itself runs 8 – 14 weeks depending on the finishes and whether the slab needs replacing. Call (888) 345-8164 for a schedule built around your specific garage.
Yes. A legal garage conversion ADU in Lomita requires building permits from the City of Lomita’s building department, and you’ll need approved plans before any work starts. We handle the submittal, plan-check responses, and inspections – pulling permits and passing inspections is part of the job, not an afterthought.
Often yes, and that’s the cheapest path. Keeping the new bathroom’s wet wall close to an existing drain line and the electrical panel near the garage limits trenching and panel work. In older Lomita garages, the structural question usually comes down to the footing and slab condition, and we check that on the first site visit before quoting.
Typically $45,000 – $130,000, with most projects landing between $50,000 and $85,000. Slab replacement, a full kitchen, a separate meter, and higher-grade finishes push a job to the top of that range. Call (888) 345-8164 for an exact quote – estimates are free.
Every garage conversion ADU we build is covered by our 730-Day Done Right Promise – if something isn’t done right, we make it right, for two full years. That covers workmanship, not just materials, and it’s in writing. Ask about it on the estimate call.
Ready for a Free Estimate on Your Garage Conversion ADU in Lomita?
Call (888) 345-8164 to schedule a free on-site estimate for your garage conversion ADU in Lomita. A live person answers around the clock, and you’ll get a written line-item quote with upfront pricing you can plan around – the number you see is the number you pay. We’ll walk the garage, talk through feasibility, and tell you honestly what it’ll take. Financing at 0% for 18 months and $1,000 off projects over $10,000 are available.
Written by the team at Groundwork Construction Co.