Tub-to-Shower Conversion in Lomita: What It Costs and How Long It Takes
A tub-to-shower conversion in Lomita usually runs $3,500 to $10,000 and takes five to eight working days from demo to final walkthrough. The job means pulling the tub and its surround down to the studs, reworking the drain and valve to a shower configuration, then building a sloped, waterproofed shower floor with new tile and glass. Most Lomita conversions land in the $5,000 to $7,500 range. Call (888) 345-8164 for a free on-site estimate.
How a Tub-to-Shower Conversion Runs, Stage by Stage

Here’s the actual sequence. Timelines assume a standard hall bath and no surprise rot behind the tile.
Stage 1: Demo and inspection, day 1 to 2
We cut the tub out and take the wall surround down, sometimes with the tub pulled whole through the door to save you a dumpster fee. The tub drain and overflow get capped, and the old valve gets exposed. This is where we learn what the 1950s-era framing in a Lomita bungalow is really doing behind the wall. You decide at this point whether the valve gets replaced or kept.
Stage 2: Rough plumbing and the drain, day 2 to 3
The tub drain sits at one end of the alcove; a shower drain belongs at center, so the plumbing has to move. We set a new shower pan liner or bonding flange, tie into the existing drain line, and reroute the supply for a shower valve. This is the stage that requires a permit and an inspection if your plumbing configuration changes, and it’s the reason a proper conversion isn’t a weekend job.
Stage 3: Substrate and waterproofing, day 3 to 4
We hang cement backer board or a foam shower board system, tape and mud the seams, and roll on a liquid waterproofing membrane or install a sheet membrane. This step gets inspected in most Lomita jobs. You choose here whether you want a curb or a curbless entry; going curbless means cutting into the floor framing and adds a few hundred dollars.
Stage 4: Tile and fixtures, day 4 to 6
Tile goes up the walls and down the floor, niche and all if you want one. This is your biggest material decision and the one that moves the price most. We set the showerhead, valve trim, and handheld on day 5 to 6, then grout and caulk.
Stage 5: Glass and final walkthrough, day 7 to 8
Tempered glass panels or a framed door go in. We test the drain, check the wall for level, and walk you through the whole thing. You sign off, and the work is covered by our 730-Day Done Right Promise.
Throughout, our technicians bring up to 12 years of experience to the framing and waterproofing details that decide whether a shower holds up for fifteen years or leaks in year three.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Shape Your Shower
- Tile vs. acrylic surround: Tile runs $2,000 to $5,000 in materials alone but lets you match the rest of the bath and lasts decades. An acrylic panel system is faster and roughly half the cost, but it reads as builder-grade and shows scratches. Most Lomita homeowners pick tile.
- Shower pan: tile-over-membrane vs. pre-formed: A tiled pan with a proper membrane is the gold standard and lets you go curbless. A pre-formed acrylic or fiberglass base is cheaper and quicker but limits your floor tile and can flex over time.
- Glass: framed vs. frameless: Frameless glass looks cleaner and keeps the small bath feeling open, which matters in a compact bungalow. It costs a few hundred more and needs a precisely level wall.
- Valve and showerhead: A standard pressure-balance valve is included in most quotes. A thermostatic valve or a rain head adds cost. Kohler is a solid name in this range.
- Niche and bench: A built-in niche is a small add. A bench means framing and waterproofing at the back wall.
What Tub-to-Shower Conversion Costs in Lomita, CA

The range is $3,500 to $10,000, and the spread comes down to five things:
- Size: A standard 30-by-60 alcove is the baseline. A wider or longer shower means more tile and glass.
- Condition behind the wall: Rot, failing galvanized pipe, or old knob-and-tube wiring adds labor and materials. We find this on day 1 and tell you before we go further.
- Moving the plumbing: Keeping the drain location saves money. Centering it or relocating the valve adds cost but is usually required for a proper shower.
- Material grade: Porcelain versus natural stone, frameless versus framed glass, and a tiled pan versus a pre-formed base all move the number.
- Permit scope: A plumbing or structural change pulls a permit and an inspection. Cosmetic swaps over existing plumbing may not.
A written estimate from us lists tile, setting materials, waterproofing, fixtures, glass, labor, permit, and disposal line by line. What’s typically not included: structural repair if we open a wall and find rotten framing, and moving a toilet or sink (that’s a wider remodel, part of our Bathroom Remodeling in Lomita work). Calls are answered by a live person 24/7, and we stand behind pricing with no change orders unless you approve them first.
See the difference
Before
After
Before
After
Before
AfterWhat Lomita Homes Do to This Job
Lomita is a built-out Harbor Gateway city of roughly one square mile, incorporated in 1964 and hemmed in by Torrance, so almost every conversion here is remodel work on the existing house rather than new construction. The building stock is mostly 1920s to 1950s bungalows on 5,000 to 6,000 square foot lots, which means we’re regularly opening a wall and finding galvanized supply lines and original framing that has to come up to code before the shower goes in. Permits run through the City of Lomita’s own building department, and its plan-check process is a small-city one layered on top of LA County’s coastal-area rules, so a plumbing change gets reviewed lot by lot. On the tight lots off Lomita Boulevard and Pacific Coast Highway, a bathroom vent or window switch often has to be worked around the neighbor’s roofline before plans go anywhere. The marine layer and salt air are a real factor inside the bath too: damp morning fog drives moisture problems, so we waterproof the full shower surround, not just the floor, and set fasteners that don’t corrode.
If your project grows past the shower into a full gut, our Bathroom Remodeling service covers the wider scope. We handle conversions across Lomita and the surrounding South Bay, and homeowners often pair a bath update with a new roof or exterior work like Metal Roofing in Lomita or Tile Roofing in Lomita while the house is already torn up.
Serving Lomita, CA – Our Local Coverage Area
We serve Lomita and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: Tub-to-Shower Conversion in Lomita

Most conversions take five to eight working days. Demo and rough-in dominate the first three days, tile fills the middle, and glass and final inspection wrap the last two. A surprise repair behind the wall can add a day or two, which we flag as soon as we see it. Call (888) 345-8164 to get a firm timeline for your bathroom.
Yes, if the plumbing changes. Moving the drain to center and swapping the valve requires a permit and an inspection through the City of Lomita. A cosmetic swap over existing plumbing may not. We pull the permit and pass the inspection as part of the job. Call (888) 345-8164 to talk through your scope.
Sometimes. If your drain and valve line up for a shower without a move, the job is cheaper and faster. But most alcoves have an off-center tub drain that has to move for the floor to slope correctly, and skipping that leads to pooling. We tell you on day 1 which case you’re in. Call (888) 345-8164 for an assessment.
The range is $3,500 to $10,000, with most jobs landing between $5,000 and $7,500. Tile grade, glass type, whether the pan is tiled, and any hidden rot or old plumbing push you toward the top. Call (888) 345-8164 for an exact quote. Estimates are free.
Every conversion we do is backed by our 730-Day Done Right Promise. If the waterproofing, tile, or plumbing isn’t right, we come back and make it right. Our technicians are background-checked and arrive in uniform. Call (888) 345-8164 to schedule your free estimate.
Get a Free Tub-to-Shower Conversion Estimate in Lomita
Ready to trade the tub for a shower your family will actually use? Call (888) 345-8164 to schedule a free on-site estimate in Lomita. We’ll measure the alcove, look behind the wall where we can, and hand you a written line-item quote with the permit and disposal included. No pressure, no vague numbers. A live person answers, day or night.