Full Bathroom Remodeling in Lomita, CA: What It Costs and How Long It Takes
Full bathroom remodeling in Lomita, CA runs $9,000 – $28,000 and takes four to six weeks of working time in a 1920s – 1950s bungalow, longer if we open walls and find knob-and-tube wiring or galvanized supply lines. That range covers a complete gut: new subfloor, backer board, tile, fixtures, vanity, lighting, ventilation and paint. Call (888) 345-8164 for a free on-site estimate, and we’ll put the scope in writing line by line.
How the job actually runs, stage by stage

A full bathroom remodel is demolition, rough-in, inspection, waterproofing, finish. Each stage waits on the one before it, and the two that get skipped by sloppy crews (inspection and waterproofing) are the ones that cost you in five years. Here’s what our technicians (up to 12 years of experience) walk you through.
Stage 1: Protect, demo, and open it up (days 1 – 3)
We mask hallways, set up dust control at the doorway, and pull the vanity, toilet and tub on day one. Demo of the tub surround and floor tile takes a day or two depending on how many layers of old material are stacked in there. You decide at this point whether the tub goes back as a tub or becomes a shower footprint – a decision that has to lock before rough-in.
Stage 2: Rough plumbing, electrical, and vent (days 3 – 7)
This is where the schedule is decided. If we’re keeping the drain and supply locations, it’s a few days. If you want the sink moved to the other wall, we’re cutting trench and running new lines. You choose vent fan location and lighting layout here – the fan has to vent to the exterior, never into the attic.
Stage 3: Inspection before anything gets covered (days 7 – 10)
The City of Lomita’s building department inspects rough plumbing and electrical before we close walls. We schedule it, meet the inspector, and correct anything flagged. No wall gets closed until it passes.
Stage 4: Waterproofing and tile (days 10 – 25)
Cement backer board, coated waterproof membrane, and a flood test on the shower pan before a single tile goes down. Tile setting, grout and a full cure takes the longest stretch of the job. You pick the tile here, and we order it early so it’s on site before this stage opens.
Stage 5: Set fixtures, finish, walkthrough (days 25 – 35)
Vanity, toilet, faucets, shower glass, lighting trim, paint, and a full leak test on every connection. Then a walkthrough where we run the shower, fill the tub, and check the fan pull before we call it done. The whole thing sits under our 730-Day Done Right Promise – if something’s not right, we make it right.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices that shape your bathroom
Most of the money and most of the regret sit in four decisions. Here’s the honest version of each.
- Tile vs. large-format porcelain vs. luxury vinyl. Ceramic is the value pick and fine for a guest bath. Porcelain handles moisture better and holds up longer in a shower. LVP is the cheapest and fastest but doesn’t belong in a wet shower. Budget roughly the same for the first two; the labor to set large-format tile runs higher.
- Tub-and-shower combo vs. separate walk-in. A combo keeps the footprint and costs less. A dedicated shower with a frameless glass panel looks better and uses the same square footage, but the glass and tile work push the number up.
- Vanity and counter choice. A stock vanity keeps the job moving. A semi-custom or custom vanity (Kohler and similar brands) adds weeks and cost, but fits an odd corner in these older Lomita bathrooms where nothing is square.
- Ventilation. A quality fan that vents to the exterior is not optional on a coastal bathroom. A cheap fan or one dumping into the attic breeds mold in a house with marine layer fog. We spec a properly sized fan every time.
- Cast iron vs. acrylic tub. Cast iron holds heat, lasts decades, and weighs a lot. Acrylic is lighter and cheaper and can flex over time. Neither is wrong – it’s a heat-retention vs. cost trade-off.
What full bathroom remodeling costs in Lomita, CA

The number lands between $9,000 and $28,000 for a full gut. A cosmetic refresh with new fixtures and paint sits near the bottom. A full tear-out with relocated plumbing, new tile throughout, a glass shower and a custom vanity lands near the top.
Five variables push a job from $9,000 toward $28,000:
- Footprint. A tight hall bath costs less than a primary bath. Tile area and fixture count scale with square footage.
- Existing condition. Rot behind the tile, a failed subfloor, or old galvanized pipe brings the number up. We can’t see it until the wall is open.
- Moving plumbing, electrical, or structure. Keeping the drain, supply, and walls where they are saves real money. Relocating any of them adds cost and inspection scope.
- Material grade. Builder-grade tile and stock vanity vs. porcelain and semi-custom.
- Permit scope. Some changes require a permit and inspection; cosmetic work generally doesn’t. We tell you which applies before we start.
A written line-item estimate lists demo, framing, plumbing, electrical, waterproofing, tile, fixtures, and paint with a price next to each. It doesn’t include surprises – if we find something behind the wall, we show you the photo and the cost before we touch it. No change orders without your sign-off.
See the difference
Before
After
Before
After
Before
AfterWhat Lomita homes do to this job
Lomita is a fully built-out Harbor Gateway city – about one square mile, incorporated in 1964, surrounded by Torrance – so almost every full bathroom remodeling job here is a gut remodel of a 1920s – 1950s wood-frame bungalow or early tract home on a 5,000 – 6,000 sq ft lot, not a new build. That means we regularly open a wall and find knob-and-tube wiring, galvanized supply pipe, or a subfloor that’s been wet for years behind a bad shower pan. The damp marine layer that rolls through Lomita in the mornings is hard on a bathroom’s waterproofing and ventilation, so we treat the shower pan flood test and the exterior-vented fan as non-negotiable. Because Lomita runs its own building department, plan check for a bathroom that moves plumbing or adds a fan runs through the City of Lomita directly – different from the process in the unincorporated pockets around it – and we schedule and meet those inspections as part of the job. Older homes near the Pacific Coast Highway and Lomita Boulevard corridors also carry the period’s quirks: out-of-square walls, low ceilings, and single-stack plumbing, all of which shape what fits and what doesn’t.
Serving Lomita, CA – Our Local Coverage Area
We serve Lomita and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Full Bathroom Remodeling in Lomita

Typically four to six weeks of working time for a hall or guest bath, five to eight weeks for a primary bath with relocated plumbing. Discovery behind the wall – rot, old wiring, a failed subfloor – adds days, not weeks, and we flag it the day we find it. Call (888) 345-8164 for a timeline on your exact layout.
Usually yes if plumbing, electrical, or structural changes are involved – a moved drain, new circuits, a vent fan added or relocated, or a wall opened for a new shower height. Cosmetic surface work generally doesn’t require one. We pull the permit and meet the inspector; the cost is part of the written estimate.
Yes, and it’s the cheaper route. Keeping the toilet, drain and supply lines where they sit and refreshing tile, fixtures and finishes keeps the job closer to the $9,000 end. Moving a drain or supply line for a better layout is the single biggest driver of cost.
Between $9,000 and $28,000 for a full gut, with a cosmetic refresh near the bottom and a fully reconfigured bath with new tile and glass near the top. Call (888) 345-8164 for an exact line-item quote – the estimate is free and on-site.
Every full bathroom remodeling project is covered by our 730-Day Done Right Promise – one of the longest workmanship guarantees in the residential construction space. If it’s not done right, we make it right. Calls are answered by a live person, 24/7.
Get a free on-site estimate for your Lomita bathroom
Call (888) 345-8164 for a free on-site estimate for your full bathroom remodeling in Lomita. We’ll walk the bathroom with you, check the plumbing, wiring and subfloor, and hand you a written line-item estimate with a real number – no vague “starting at” pricing. Upfront pricing, no surprises. If your project grows into a larger scope, our bathroom remodeling service and Bathroom Remodeling in Lomita pages cover the wider work, and we serve the full Lomita area. Homeowners often pair this with Roof Repair in Lomita if the marine layer has been hard on the roofline, or Roof Replacement & Installation in Lomita when it’s time for a full envelope update.